SpaceX Starship page

FAQ

  1. When next launch? (Flight 14) NET September 18th.
  2. When previous launch? (Flight 13) Starship flight 13 launched on 2026-07-24.
  3. What was the result? Successful liftoff and staging. B20 had a good boostback burn, but landing burn had insufficient engines. S40 performs perfectly, with nominal payload deploy and in-space raptor relight. Ship reentry, landing burn, are nominal, and S40 remains intact after splashdown.

Previous Flights

Click to expand

  • Flight 1: S24 and B7. First full stack launch, RUD before stage separation.
  • Flight 2: S25 and B9. Successful stage separation, booster RUD during boostback burn, ship RUD shortly prior to scheduled SECO.
  • Flight 3: S28 and B10. Booster performs a successful boostback burn, but experiences RUD during landing burn. Ship makes it past SECO, but loses attitude control and is destroyed on reentry.
  • Flight 4: S29 and B11. First successful booster water landing. Ship survives reentry despite burn-through on forward flap, and performs a successful water landing.
  • Flight 5: S30 and B12. First booster catch with chopsticks. Ship performs successful water landing.
  • Flight 6: S31 and B13. Booster offshore divert due to damage to catch tower during launch. Ship performs successful water landing.
  • Flight 7: S33 and B14-1. First V2 Ship launch. Harmonic oscillation on ship causes RUD before SECO. Booster is caught by chopsticks.
  • Flight 8: S34 and B15-1. Engine failure on ship causes RUD before SECO. Booster is caught by chopsticks.
  • Flight 9: S35 and B14-2. First booster reflight. Ship makes it past SECO, but loses attitude control and is destroyed on reentry. Booster RUD upon landing burn startup prior to planned splashdown.
  • Flight 10: S37 and B16. All mission objectives fulfilled. First V2 ship to make it through reentry to landing burn and splashdown. First successful deployment of Starlink simulators. Booster successfully tested landing without one centre engine, using an engine on the middle ring to compensate.
  • Flight 11: S38 and B15-2. All mission objectives fulfilled. Ship performs successful landing burn and splashdown, despite intentional missing tiles on heatshield. Second successful deployment of Starlink simulators. Booster successfully tested a 13-5-3 engine landing profile.
  • Flight 12: First V3 launch. Successful liftoff. Booster boostback burn is incomplete, and landing burn fails. Ship experiences an R-vac out shortly after stage separation, but limps to orbit on 5/6 engines. In-space raptor relight is cancelled, but payload deployment is nominal. Ship reentry, landing burn, and splashdown are nominal.
  • Fight 13: Successful liftoff and staging. B20 had a good boostback burn, but landing burn had insufficient engines. S40 performs perfectly, with nominal payload deploy and in-space raptor relight. Ship reentry, landing burn, are nominal, and S40 remains intact after splashdown.

Quick Links

Nerdle Cam | Lab Cam | Sapphire Cam | Sentinel Cam | Rover Cam | Rover 2.0 Cam | Rocket Ranch Cam | Plex Cam | NSF Starbase Live | afarTV Florida Gigabay Live

Starship Dev August | Starship Dev July | Starship Dev June | Starship Dev May | Flight 12 | Starship Dev April

2026-04-27 SpaceX Starship Update Video


Road closures, road delays, and beach closures

Vehicle Status

*As of 2026-08-30

Ship Location Status Comments
S39.1 (test tank) Production site (NSF, ViX, TrackingTheSB)
S40 Indian Ocean Destroyed Stacking took place from Nov 12th through March 2nd. Cryo testing from May 3rd through May 6th. Engine testing Jun 24th through 26th. Launched Jul 24th.
S41 Pad 2 Chopsticks testing April 17th: Pez Dispenser moved into MB2. April 20th: Nosecone+Payload Bay stack N:3 moved into MB2 and later that day lifted over the Pez Dispenser. Later that day the Pez Dispenser was installed. April 21st: Forward Dome section FX:4 moved into MB2. April 28th: Common Dome Section CX:3 moved into MB2. May 2nd: Section A2:3 moved into MB2. Cryo testing Jun 28th to Jul 6th. Static fired Aug 19th and 20th.
S42 Megabay 2 Pending engine installation Stacking began Jul 11th. Cryo tested Sep 3rd and 4th. Chopsticks testing Sep 11th and 12th.
S43 Megabay 2 Stacking Stacking began around Aug 19th.
S43.1 (test tank) Massey's Testing
S44 Starfactory
Booster Location Status Comment
B18.1 Massey's Testing
B18.3 Massey's Testing
B20 Gulf of Mexico Destroyed Stacking took place from Feb 5th through Apr 30th. Cryo tested Jun 6th through Jun 8th. Launched July 24th.
B21 Megabay 1 Pending FTS install Stacking began Jun 4th, completed Jun 28th. Cryo testing Jul 17th through Jul 22nd. Static fired Aug 28th.
B22 Megabay 1 Pending engine installation Stacking started Jun 29th. Cryo tested Sep 9th.
B23 Megabay 1 Stacking Stacking started around Aug 14th.

Resources

top 13 comments
sorted by: hot top controversial new old

2026-09-14:

  • Pad 1: The concrete pour for the flame trench centre floor is completed. 250+ truckloads were delivered over the course of 16 hours. (ViX, TrackingTheSB, lewisknaggs42)
  • Some cladding is installed near the top of Tower 1. (ViX, ViX 2)
  • Pad 2: A chopstick actuator is removed. (ViX)
  • A deluge test is observed. (TrackingTheSB, RGV Aerial)
  • Other: 51 foundation footings are now visible at the new 444-acre site along Highway 4 near Starbase. (RGV Aerial photo, RGV Aerial video)
  • S40 recovery: Forte passes the tip of South Africa. (marinetraffic.com)
  • Flight 14: Earliest launch windows are now Sep 22nd and 23rd, both 12:15 to 14:14 UTC (07:15 to 09:14 local). (fly.faa.gov, archive, Avid Space)
  • Elon confirms no ship catch for this flight. (outerspacetoday)
[–] threelonmusketeers@sh.itjust.works 2 points 1 day ago* (last edited 1 day ago)

2026-09-13:

  • Sep 12th addendum: Timelapse of S42 chopsticks and ship quick disconnect testing. (RGV Aerial)
  • Production site: Overnight, S42 moves from Pad 2 to Megabay 2. (NSF, Avid Space, ViX, TrackingTheSB, RGV Aerial, efraser77)
  • S43 has been lifted over top of the transfer tube installation jig. (ViX, Blobifie)
  • Massey's: A booster cryo stand and a ship static fire stand are moved from the production site to Massey's for storage. (NSF, TrackingTheSB)
  • Pad 1: A lengthy concrete pour begins for the flame trench. 122+ truckloads are delivered over the course of 8+ hours, with three pump trucks running concurrently. (ViX, TrackingTheSB, lewisknaggs42)

2026-09-12:

2026-09-11:

[–] threelonmusketeers@sh.itjust.works 3 points 4 days ago* (last edited 2 days ago)

2026-09-10:

[–] threelonmusketeers@sh.itjust.works 3 points 6 days ago* (last edited 6 days ago)

2026-09-08:

  • Sep 7th addendum: The new roof for Tower 1 is relocated by SPMTs. (ViX)
  • Pad 1: The yellow rented LR11000 crane lifts the roof off the ground, but sets it back down shortly after. (ViX, ViX)
  • Pad 2: Overnight, the launch mount service structure rolls out to Pad 2. (NSF, Avid Space, ViX)
  • The chopsticks, landing rails, and stabiliser arms are tested. (ViX)
  • The booster quick disconnects, hold-down clamps, ship quick disconnect arm, and ship quick disconnect perform a fast retraction test. (ViX 2, ViX 2)
  • A launch and landing deluge test is performed. (ViX 1, ViX 2, Blobifie)
  • Massey's: Overnight, B22 moves from Megabay 1 to Massey's. (NSF, Avid Space, ViX, StarshipGazer, cnunez 1, cnunez 2, Blobifie 1, Blobifie 2)
  • Road delays for "Production to Masseys" are posted for Sep 8th 23:59 to Sep 9th 04:00 and Sep 9th 23:59 to Sep 10th 04:00. (starbase.texas.gov, archive, ViX)
  • Production site: B23's aft section enters Megabay 1. (ViX)
  • B23's LOX landing tank enters Megabay 1. (ViX)
  • A bridge crane girder section is staged outside of the Gigabay. (ViX, Gisler)
  • The crane which was obstructing the Avid Space Rover 1 camera is moved. (ViX)
  • The bridge crane girder section enters the Gigabay. (ViX)
  • The girder section is offloaded from the transport in the Gigabay, and the Megabay 2 bridge crane lifts the two-point ship lifting jig. (ViX)
  • The girder section is moved over to the left side of the Gigabay. (ViX)
  • Ship cryo stand enters Megabay 2. (Avid Space, ViX, Blobifie)
  • McGregor: R3.240 (new highest) and R3.237 head towards the testing area. (SpaceRhin0 1, SpaceRhin0 2)
  • R3.236 returns from its 3rd round of testing. (SpaceRhin0)
  • S40 recovery: Forte is currently anchored off the coast of Madagascar, likely waiting for weather to improve. (interstellargw)
[–] threelonmusketeers@sh.itjust.works 3 points 1 week ago* (last edited 1 week ago)

2026-09-07:

  • Massey's: Road delay for "Production to Masseys" is posted for Sep 7th 23:59 to Sep 8th 04:00. (starbase.texas.gov, archive, ViX)
  • Launch site: Road delay for "Production to Pad" is posted for Sep 7th 23:59 to Sep 8th 04:00. (starbase.texas.gov, archive, ViX)
  • Production site: Gigabay construction continues. (cnunez)
  • The launch mount servicing structure has been transferred to SPMTs. (Anderson)
  • Booster aft section is (probably) fit checked with the horizontal booster transportation frame. (ViX)
  • Booster lifting jig is hoisted in Megabay 1. (ViX)
  • Booster cryo stand enters Megabay 1. (Avid Space, ViX)
  • B22 is transferred to the cryo stand. (efraser77, Blobifie)
  • McGregor: R3.236 returns from the testing area. (SpaceRhin0)
  • Florida: Venting from Pad 39A is observed. (NSF)

2026-09-06:

[–] threelonmusketeers@sh.itjust.works 3 points 1 week ago* (last edited 1 week ago)

2026-09-01:

  • Production site: Overnight, the ship cryo stand arrives at Megabay 2. (ViX)
  • S43's A2 section moves from Starfactory to Megabay 2. (ViX, Blobifie)
  • Ship cryo stand enters Megabay 2. (Blobifie)
  • Pad 1: The weather mast is removed from the launch tower. (NSF, Avid Space, ViX, Blobifie)
  • Massey's: New temporary flight restriction is posted for Sep 1st 19:23 UTC to Sep 2nd 19:23 UTC, presumably for S42 testing, though the ship has not yet rolled out. (FAA, Avid Space)
  • Road delay for "Production to Masseys" is still listed for Sep 1st 23:59 to Sep 2nd 04:00. (starbase.texas.gov, archive, ViX)
  • McGregor: Raptor 3 sea level mockup heads towards the testing area. (NSF, Rex_MKR)
  • A Raptor 3 vacuum engine returns from the testing area. (SpaceRhin0)

2026-09-05:

  • Brownsville Port: A horizontal ship transport frame moves from Brownsville Port to the production site. (NSF, ViX)
  • Massey's: Road delay for "Masseys to Production" is posted for Sep 5th 23:59 to Sep 6th 04:00. (starbase.texas.gov, archive)
  • Florida: A horizontal ship transport frame and a booster stand are moved from Roberts Road to the KSC turn basin, staged for shipment to Starbase Texas. (NSF, Avid Space, ViX, Golden)

2026-09-04:

  • Overnight, S42 completes its 2nd cryo test. (ViX, Blobifie)
  • Brownsville Port: Road delay for "Port to Production" is posted for Sep 4th 23:59 to Sep 5th 04:00. (starbase.texas.gov, archive)
  • Massey's: Speculation on some of the structural tests conducted on S43.1. (Killip 1, Killip 2)
  • Production site: S43's A3 section enters Megabay 2. (ViX, Blobifie)
  • The launch mount service structure has been stacked and the plates have been bolted together. (Killip 1, Killip 2)
  • All four corner sections and all four middle sections of the Pad 1 launch mount are now in place. (Killip)
  • Pad 2: Movement of the chopsticks, landing rails, and ship quick disconnect arm are observed. (ViX)
  • The tower vent pipe is removed. (ViX)
  • Highlight of the bolts used to connect the columns of the tower into the base, likely for protection from Raptor exhaust when gimballing during launch. (Killip)
  • McGregor: The previous evening, a sea-level Raptor headed towards the testing area. (SpaceRhin0)
  • R3.236 (new highest) returns from the testing area. (SpaceRhin0)
  • S40 recovery: Forte still scheduled to arrive at Starbase on Oct 8th. (interstellargw)

2026-09-03:

  • Sep 2nd addendum: The S43.1 nosecone performs a cryo test. (ViX)
  • Massey's: S42 begins its first cryo test. (Avid Space, ViX)
  • Recent flyover photo of S42. (RGV Aerial)
  • Road delay for "Masseys to Production" is posted for Sep 3rd 23:59 to Sep 4th 04:00. (starbase.texas.gov, archive, ViX)
  • The booster cryo stand departs from Massey's. (ViX)
  • Production site: The raceways for S43 are staged on the central work area of Megabay 2. (Avid Space, ViX)
  • Installation of flight termination systems on B21 and S41 is underway. (RGV Aerial)
  • Grading work is observed near Highway 4 and the Brownsville Port access road. (RGV Aerial)
  • Pad 1: Installation of pipes for the deluge system is underway. (ViX)
  • Pad 2: Additional cladding is installed on the launch tower. (ViX 1, ViX 2)
  • Movement of the chopsticks and the ship quick disconnect arm are observed. (ViX)
  • McGregor: R3.106 (vacuum engine) and R3.134 head back for more testing. (SpaceRhin0)
  • Other: Visualization of various orbital planes for Starship and subsequent RTLS opportunities. (mcrs987)

2026-09-02: