SpaceX Starship page
FAQ
- When next launch? (Flight 14) NET August.
- When previous launch? (Flight 13) Starship flight 13 launched on 2026-07-24.
- What was the result? Successful liftoff and staging. B20 had a good boostback burn, but landing burn had insufficient engines. S40 performs perfectly, with nominal payload deploy and in-space raptor relight. Ship reentry, landing burn, are nominal, and S40 remains intact after splashdown.
Previous Flights
Click to expand
- Flight 1: S24 and B7. First full stack launch, RUD before stage separation.
- Flight 2: S25 and B9. Successful stage separation, booster RUD during boostback burn, ship RUD shortly prior to scheduled SECO.
- Flight 3: S28 and B10. Booster performs a successful boostback burn, but experiences RUD during landing burn. Ship makes it past SECO, but loses attitude control and is destroyed on reentry.
- Flight 4: S29 and B11. First successful booster water landing. Ship survives reentry despite burn-through on forward flap, and performs a successful water landing.
- Flight 5: S30 and B12. First booster catch with chopsticks. Ship performs successful water landing.
- Flight 6: S31 and B13. Booster offshore divert due to damage to catch tower during launch. Ship performs successful water landing.
- Flight 7: S33 and B14-1. First V2 Ship launch. Harmonic oscillation on ship causes RUD before SECO. Booster is caught by chopsticks.
- Flight 8: S34 and B15-1. Engine failure on ship causes RUD before SECO. Booster is caught by chopsticks.
- Flight 9: S35 and B14-2. First booster reflight. Ship makes it past SECO, but loses attitude control and is destroyed on reentry. Booster RUD upon landing burn startup prior to planned splashdown.
- Flight 10: S37 and B16. All mission objectives fulfilled. First V2 ship to make it through reentry to landing burn and splashdown. First successful deployment of Starlink simulators. Booster successfully tested landing without one centre engine, using an engine on the middle ring to compensate.
- Flight 11: S38 and B15-2. All mission objectives fulfilled. Ship performs successful landing burn and splashdown, despite intentional missing tiles on heatshield. Second successful deployment of Starlink simulators. Booster successfully tested a 13-5-3 engine landing profile.
- Flight 12: First V3 launch. Successful liftoff. Booster boostback burn is incomplete, and landing burn fails. Ship experiences an R-vac out shortly after stage separation, but limps to orbit on 5/6 engines. In-space raptor relight is cancelled, but payload deployment is nominal. Ship reentry, landing burn, and splashdown are nominal.
- Fight 13: Successful liftoff and staging. B20 had a good boostback burn, but landing burn had insufficient engines. S40 performs perfectly, with nominal payload deploy and in-space raptor relight. Ship reentry, landing burn, are nominal, and S40 remains intact after splashdown.
Quick Links
Nerdle Cam |
Lab Cam |
Sapphire Cam |
Sentinel Cam |
Rover Cam |
Rover 2.0 Cam |
Rocket Ranch Cam |
Plex Cam |
NSF Starbase Live |
afarTV Florida Gigabay Live
Starship Dev July | Starship Dev June | Starship Dev May | Flight 12 | Starship Dev April | Starship Dev March
2026-04-27 SpaceX Starship Update Video
Road closures, road delays, and beach closures
Vehicle Status
*As of 2026-08-01
| Ship |
Location |
Status |
Comments |
| S39.1 (test tank) |
Production site |
(NSF, ViX, TrackingTheSB) |
|
| S40 |
Indian Ocean |
Destroyed |
Stacking took place from Nov 12th through March 2nd. Cryo testing from May 3rd through May 6th. Engine testing Jun 24th through 26th. Launched Jul 24th. |
| S41 |
Megabay 2 |
Pending engine install |
April 17th: Pez Dispenser moved into MB2. April 20th: Nosecone+Payload Bay stack N:3 moved into MB2 and later that day lifted over the Pez Dispenser. Later that day the Pez Dispenser was installed. April 21st: Forward Dome section FX:4 moved into MB2. April 28th: Common Dome Section CX:3 moved into MB2. May 2nd: Section A2:3 moved into MB2. Cryo testing Jun 28th to Jul 6th. |
| S42 |
Starfactory |
Stacking |
Stacking began Jul 11th. |
| S43.1 (test tank) |
Massey's |
Testing |
|
| Booster |
Location |
Status |
Comment |
| B18.1 |
Massey's |
Testing |
|
| B18.3 |
Massey's |
Testing |
|
| B20 |
Gulf of Mexico |
Destroyed |
Stacking took place from Feb 5th through Apr 30th. Cryo tested Jun 6th through Jun 8th. Launched July 24th. |
| B21 |
Megabay 1 |
Pending engine installation |
Stacking began Jun 4th, completed Jun 28th. Cryo testing Jul 17th through Jul 22nd. |
| B22 |
Megabay 2 |
Stacking |
Stacking started Jun 29th. |
Resources
2026-08-05: